Steel construction for hall placed in week 6 and 7
In the middle of week six, Van Zoggel construction company started placing the steel supporting structure of the new premises.
This work was completed at the end of week seven.
The casement frames on the first floor of the offices were also installed in week seven.
Despite the bad weather, the gluing work, carried out by Michel v.d. Brand, continued unabated.